Planned Work - DC Mains Power Testing from 2020-11-03 00:00 NZST to 2020-11-03 01:30 NZST

Scheduled maintenance Voice SIP Registration SIP peering WL National International Broadband Chorus Enable TFF North Power Web Portals API Billing Legacy MCT
2020-11-03 00:00 NZST · 1 hour, 30 minutes

Updates

Scheduled

Hazard notification only. Data Centre provider has advised testing on mains power in one of the Data Centres that our equipment is hosted in. Due to UPS and Generators there should be no impact to services. Apologies for the short notice.